Friday, October 28, 2011

Day 43

We had a snowstorm this week, and lost power for most of a day, so nothing happened on Wednesday.  Thursday was Day 43 of actual work, and we are now at 8 weeks since construction started.



The electrical trim out got finished today, which included hanging our new pendant lights.  It was dark outside when I was taking pictures, so I'll have to get some lighter ones.  That tile wall was finally finished today!  That was a whole lot of tile cutting.  I think it looks fabulous.  It will get grouted next week, and then the shelves can go up.



Down in the basement the rest of the doors were hung, and hardware installed.  This is the mechanical room door.



This is the freshly painted quarter round that will line the baseboard in the rooms with laminate.  It covers the gaps where the floor isn't level.



Our office closet doors.