Saturday, September 17, 2011

Day 15

The plumbers came today, even though its Saturday.  I think we're having an inspection on Monday, and stuff had to be done.


The master bathroom sink is ready.



And the shower got set today.  The stupid concrete slab slopes 3/4 of an inch along the length of the shower, so they had to pour 80 pounds of concrete under there to level it out.



This is the doorway that got framed yesterday.  It will be SO much nicer not to look in the messy coat room.

Day 14

More wiring work today.  Lots more.  I wasn't surprised in the least to hear the electrician say that 1 job in 10 turns into the mess from hell, and mine is one of the ones, lol.  The kind you can't predict until you start tearing into it.  Today he opened up a box and said 'Wow, what on earth were they trying to do?  There is no way an electrician did this'.  Great...I'm trying not to think about the rest of the house that isn't being redone.

That doorway that I changed my mind about got framed down to the right size, but I didn't feel like going down to take a picture.

Friday, September 16, 2011

Day 13

A lot more went on with electrical wiring and plumbing, but not stuff that is easy to see in pictures.


Installed the 6 new can lights and 2 pendants in the kitchen.  Took out the 2 old cans that were in the wrong place now.



Got rid of the old plumbing for the sink and added the gas connection for the new stove.



Added the plumbing for the new sink.  Lots of other plumbing stuff went on today, but I don't know what it was, lol.


We did make lots of decisions today.  Now that we can see the walls and size of the spaces, we opted to scratch 3 of the can lights in the basement that we had planned.  We hadn't made up our mind about lighting in the master bedroom, so we did that.  We're going with 4 sconces on the walls and 1 in the hallway.  We still haven't decided about a ceiling fan in our bedroom, so we opted to wire for it and decide later, after we live in the space for awhile.  Decided to go with a fluorescent fixture in the master closet, rather than incandescent.  Decided to go ahead and pay extra to fix that sloping floor in the basement so we can have laminate instead of carpet in the main sitting area.  And here's the one decision I felt just a little bad about -


I stood where the couch is going to be and realized that if we look right, we'll be looking right into the coat closet (left of the stairs).  I don't want to see that, so we're going to make that doorway smaller.  On the plus side, its a LOT easier to make it smaller than bigger.



Lots of wiring went on again today, which is very hard to show.  The basement wiring was all wrong too, so it had to all be redone.  The Jacuzzi tub upstairs was wired wrong, so that had to be fixed too.  

This photo is looking into the master bedroom, you can kind of see the ceiling and how its framed to drop down halfway across the room.  It has to in order to enclose the plumbing, but its going to look too choppy like that, so we decided to drop the whole ceiling down.  It won't be as tall but will make me happier in the end.  The drywall guys will be happier too.

Wednesday, September 14, 2011

Day 12


Aw, the psych ward door is finally gone.  At least I'll always have pictures.



Installing a heavy-duty lintel so the house doesn't fall down through that new, extra-wide doorway.



Doorway is done.  I wish my kids cleaned up after themselves half as well as these guys do!



A bunch of plumbing stuff happened today.  This is the drain from the laundry room upstairs.  It now runs through the wall like its supposed to, rather than stuck out in the middle of the room.  This will be a little sink and fridge cabinet so we can make coffee without having to go upstairs.



Moved the plumbing around for the new bathrooms.



This will be the new master shower.  Yes, I know its fiberglas, and not some gorgeous tile, and people think we're weird for choosing this.  But, I've had enough mildewed grout (Florida = steamy pits of hell) to last a lifetime.  Easy to clean is so much more important than looks at this point.

Monday, September 12, 2011

Day 11


Remodeling is such an adventure, you never know what you'll find once its too late to turn back, lol.  The wiring in the kitchen turned out to be even wonkier than we first thought, so the whole thing is getting rewired now.  Sheesh.  I'd really like to smack whoever thought making such a mess of it was a good idea.  All that drywall wasn't originally supposed to come off like that, but its going to be easier to replace the big 4-foot sections rather than patch a bunch of smaller areas.



Wires running through the new bar, and that hideous light is gone!



The nasty tile at the top of the stairs is gone.



The carpet is gone.  That ugly wallpaper will go at some point, but not as part of this job.



The door to the basement will be opened up.



The one support column that wouldn't fit into a wall is getting covered.



This is our bedroom ceiling.  The soffitt covering the plumbing is up.



WooHoo!  Our new A/C compressor is in.  Being from Florida, I've never seen one this tiny, lol.  It looks like a toy.

Saturday, September 10, 2011

Day 10


A lot happened in the basement today, but not stuff that can be seen well in pictures.  The electrician spent a lot of time tracing stuff, fixing stuff that made no sense, etc.  The HVAC guy is up there running tubing that will go out to the new A/C compressor (yay!).  I don't really know what else he's doing down there, but I'm glad he's doing it, lol.
  


Whoops, forgot to lighten this picture up.  Anyway, I'm working on hacking some of these bushes out so the compressor can go here.  Those lower windows are proving pretty handy for  getting stuff into the basement.  Passing it through there beats the heck out of hauling everything around the corner and down the stairs.



Meanwhile, back up in the kitchen, the drywall came down here.  This is where the stove was, and where the new sink will be.  It does tend to give you pause when the electrician comes in, takes one look, and says Wow.  



This is what he's looking at.  Really, would it have take SO much longer to do the job right, rather than slap wires together with what looked like an entire roll of tape??  We've been finding stuff like this everywhere since we moved in.  Things that make you say either Hmmm, or What on EARTH were they thinking?!?



Here's another of those things.  Its hard to see here, but apparently they got a new fridge at some point that didn't quite fit, so they cut the wall out.  They didn't even do it straight, it came to a V at the bottom.  


Now it will be a straight wall, and come out far enough to cover the new cabinet-depth refrigerator.  It kills me to pay more money for less space in a cabinet depth fridge.  But, since we have so little floor space in the kitchen I'm choosing to look at it as paying for more floor space, not less fridge space.



Framed out for the new window over the sink.  You can see where they used to have a vent for the stove, but that was covered by the drywall.  I still can't imagine having no venting for the stove.  Maybe they never burned stuff like I do...



The new bar wall is framed.  I think the awful fluorescent light box is coming down on Monday.  We'll be adding more can lights in the ceiling, and the two that are there will be replaced by pendant lights.  We still have to shop for those.

Thursday, September 8, 2011

Day 9


It was a pretty big day today.  Downstairs the new furnace went in.  The old one was 28 years so it was time...



We lost the kitchen today!!  I was SO excited!  But not fast enough with the camera because John had the countertops and the bar cabinets out of there SO fast.



That big circle was a lazy susan.  We'll have 2 of those in the new kitchen.  These cabinets were built in place, so it wasn't pretty taking them apart.  If you look closely, you can see that all of the insides were really ugly plywood.  Guess that's why the previous owners covered everything with contact paper (which was also ugly)



And...there goes the flooring.  All of the tile and the layer of subfloor under it.  



This is what is left at the end of the day.  The stove is going to friends tomorrow.  The trash can and buckets are covering heating vent holes.  Apparently there was an old, unused register inside the cabinet.



Sophie checking out the changes.  That yellow hideousness is the original linoleum floor, and was the footprint of the original kitchen.  This house was built in 1964.  Wow, what a tiny kitchen!



There are LOTS of nails sticking up everywhere, so the plastic is staying up for now.  At some point all those nails have to come out or get pounded in before the new floor can go in.



And here's the sink, sitting outside.  How trailer trash is that??  Its there because I asked them to save it for me.  I'm thinking of using it for a garden/potting area sink at some point.  Or we can use it in the barn, when we build one.  Oh, so many projects...